FM 518 and Wesley Drive Drainage Project Update

The construction around FM 518 and Wesley Drive is aimed at a specific problem: stormwater that exceeds the capacity of the existing drainage system. League City is enlarging that system and adding infrastructure to carry runoff toward Corum Ditch, according to the city's project description.

For residents who pass through the area, the visible roadwork is one part of an underground drainage project.

What the construction includes

The city's construction bid documents describe concrete drainage boxes, connecting storm sewer pipes, curb inlets and junction boxes along FM 518, Wesley Street and North Wesley Drive. The scope also requires rebuilding pavement disturbed by installation. Work within the state roadway's right of way must follow Texas Department of Transportation requirements, with construction sequencing and traffic control coordinated with TxDOT. The contract also requires stormwater pollution prevention measures during construction to minimize erosion.

The latest dated construction captions available on the League City Listens project page describe July 2026 work. They report temporary traffic controls and business access along FM 518, driveway preparation, and excavation for a junction box. Those updates document progress during July; they do not establish today's lane configuration.

The schedule has two distinct phases

The project page lists November 2026 as the updated target for substantial completion of Phase 1. Weather and unforeseen conditions could change that schedule. Phase 1 status.

Phase 2 is intended to improve drainage and rehabilitate pavement along Wesley Street, Highland Terrace Drive and Loch Lomond Drive. Its posted description still refers to 90% design and anticipated summer 2026 bidding and construction. That older forecast does not confirm that Phase 2 has started. Phase 2 description.

Why the project took time to reach construction

The city's December 2025 status report describes funding and approval complications before work moved forward. A grant funding discrepancy prompted coordination with state emergency management officials, and the city reported that changed federal guidance affected the project's benefit-cost eligibility. Staff then chose to seek bids using other funding. That history helps explain why older project references can describe planning and bidding, even though later updates show construction. City project history.

Where residents can follow progress

League City's interactive project map provides another way to follow capital projects. Its markers distinguish preliminary work, design, construction and recently completed projects. Selecting a project opens its description, tentative schedule and project manager's contact information. The city recommends using the map alongside its weekly City Manager's Updates.

For questions specifically about the FM 518 and Wesley Drive project, the city lists project manager Jaime Dino at 281-554-1487. Project contact information.